McAlpine Creek - Sardis Road to Providence Road
A nearly one-mile section of McAlpine Creek received a major makeover to improve water quality. In addition, two storm water ponds near this section of creek were improved and a wetland was enhanced. 

Completed: December 2011

Objectives:
  • Restore the stream path to a more natural design, stabilizing and reshaping banks 
  • Reduce bank erosion
  • Measurably reduce the amount of sediment and other pollutants in McAlpine Creek and some tributaries
  • Preserve open space along the creek
  • Improve aquatic habitat for fish and other wildlife by putting stream structures in the creek that increase oxygen levels within the water
  • Repair storm water ponds and enhance wetlands

Final project mailer (December 2011) ​

Stream with eroded banks  Stream is partially restored  Restored stream 

 March 2010

 February 2011

 October 2012

Stream restoration
McAlpine Creek is on the State's list of impaired waterways because of high levels of bacteria and sediment.    

The amount of storm water runoff and the speed at which that water flows have both been increasing. Fast-moving water had eroded McAlpine's banks, leaving them jagged and unstable. Bank erosion had also caused high levels of soil particles in the water.

Storm Water Services repaired the eroded banks and returned them to a natural state. The stream work will not prevent the creek from flooding. Storm Water Services is repairing the erosion damage and restoring the stream bed and banks. The result will be improved water quality and aquatic habitat. 
Muddy area where pond is being constructed  Completed pond and wetland 

 March 2011

 December 2011

Retention pond repair
As part of this project, two storm water retention ponds were repaired and nearby wetlands were improved. These Best Management Practices will remove some pollutants from the water. And retention ponds slow the flow of water by holding some excess runoff during heavy rain. That will reduce creek bank erosion.

Total cost: $2.04 million

Sources of funding:
Charlotte-Mecklenburg Storm Water Services: $1.2 million
North Carolina Clean Water Management Trust Fund: $845,000

Project schedule:
    Planning and design:
  December 2007 to July 2009
    Construction:  December 2009 to December 2011
                            Blythe Development Co.

Contact:
Brian Sikes
Project Manager
Charlotte-Mecklenburg Storm Water Services
704-336-3729