Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Dogwood Place Pond Rehabilitation
The objectives of the Dogwood Place Pond Rehabilitation Project are to preserve and enhance water quality benefits for downstream waters and to provide improved flood control benefits. These objectives will be achieved by rebuilding the outlet structure of the pond.  The project has completed construction. 

 

Dogwood Place Project Area.

Final cost: $455,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.

The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Dogwood Place Pond Rehabilitation Project through the phases listed below.
Planning Phase (Completed April 2010)
During the planning phase, several improvement alternatives were developed and evaluated to determine the best solution.  A recommended alternative was selected and used as a guide for the design. 

Design Phase (Completed February 2011)
The engineering consultant is working closely with Storm Water Services to develop and finalize the design.  Personnel from City of Charlotte, the engineering consultant, land surveyors, wetland specialists, and geotechnical engineers will be working in the area collecting information necessary to complete the design.

Permitting Phase (Completed January 2011)

During the permitting phase, the required water quality permits are obtained from Federal and State governments.  Other permits such as permission to work within CMU rights-of-way will be obtained during this phase.  The permitting phase of a project may overlap other phases.

Property Easement/Acquisition (Completed August 2010)
The City works with citizens and businesses to acquire Storm Drainage Easements (SDEs) and Temporary Construction Easements (TCEs).  The City requests that SDEs and TCEs be donated to provide access to the affected properties to make the recommended improvements and provide future maintenance.  Hickory Grove Baptist Church and several homeowners provided the essential easements during 2010.

Bid Phase (Completed June 2011)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process.  By state law, the lowest responsible bidder is awarded the construction contract.  The bid phase of a project typically lasts 4 to 5 months.

Construction Phase (Completed January 2012)
Throughout construction, efforts will be made to minimize disruption to nearby property owners.  Construction of proposed improvements will be supervised by a City Inspector.  Notifications of key construction dates and will be mailed to residents prior to construction.  There are two noticeable phases on projects like this one: major construction and revegetation.  The major construction work will be completed in the first six to nine months, weather permitting.  Major construction involves earth work, concrete work, roadway repaving and other activities typically associated with a construction project.  After the major construction is complete, the revegetation phase will begin.  This phase takes a couple growing seasons and is susceptible to things like drought.

Project Team
  

David N. Perry, P.E.
City Project Manager
704-336-4202
 
Charlotte Drzewiecki
City Construction Inspector
704-361-7597

Gary Stansbury
City Construction Manager
704-336-2667

Amy Bice, E.I. 
Watershed Area Manager
704-432-0965

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183

Newsletters

August 2011
April 2011
December 2010
August 2010