Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Cutchin Drive Storm Drainage Improvement Project
The Cutchin Drive Storm Drainage Improvement Project (SDIP) is within a drainage area of approximately 160 acres and the improvements may include culvert replacements, pipe system upgrades and channel improvements. The project boundaries are, roughly speaking, Sharon View Road to the north, Wamath Drive and Mountainbrook Road to the south, McMullen Creek to the east and Sharon Road to the west.
Cutchin Drive project area map
 
Objectives:

- Reduce structure and street flooding.

Cost:  To Be Determined
Please note that this figure will include all costs associated with this project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.
​The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Cutchin Drive Storm Drainage Improvement Project through the phases listed below. General descriptions and ranges of typical timeframes for project phases are given below. Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project. Public meeting will be held throughout the project with the affected property owners to present the planning and design information and receive input.
 
Planning Phase (Began April 2014)
During the planning phase, public meetings are used to obtain input from property owners. Several improvement alternatives are developed and evaluated to determine the best solution. A recommended alternative is presented to the public for comment at the end of the planning phase. The planning phase of a project typically lasts 12 to 27 months. 
 
Design Phase (Time frame TBD)
During the design phase, construction drawings are developed for the alternative selected during the planning phase. Many details must be addressed including the determination of specific pipe sizes and alignments, channel widths and lining types, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.
 
Permitting Phase (Time frame TBD)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way may also be obtained during this phase if necessary. The permitting phase of a project typically lasts 3 to 9 months; however, it may overlap other phases.
 
Property Easement/Acquisition (Time frame TBD)
The City's real estate staff works with citizens and businesses to acquire Storm Drainage Easements (SDEs). The City requests that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance. In addition to SDEs, temporary construction easements may be needed to access work areas. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.
 
Bid Phase (Time frame TBD)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 5 to 6 months.

Construction Phase (Time frame TBD)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates and will be mailed to residents prior to construction. Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.

Project Team

Adrian Cardenas, P.E.
Project Manager
704-336-4682

Doug Lozner, P.E.
Watershed Area Manager
704-432-0964 

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183

Newsletters

August 2014 
April 2014