Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Bongaard Pond and Dam Improvement Project

The objective of the Bongaard Pond and Dam Improvement Project is to preserve and enhance water quality benefits for downstream waters. These objectives will be achieved by rebuilding the outlet structure and dam of the pond.

 
 
In addition this project will include flood control improvements as the culvert under Middle Acres Road leading to the pond is undersized. The project is currently in the Construction Phase.
 
Estimated Cost:  $1,000,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.
 
The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Bongaard Pond and Dam Improvement Project through the phases listed below.


Feasibility/Planning Phase (April 2011- November 2011)

During the feasibility/planning phase, the existing conditions of the pond and the road were evaluated and several improvement alternatives were developed.  These alternatives were evaluated to determine the best solution and a recommended alternative was selected and used as a guide for the design.

Design Phase (November 2011 - June 2012)
The engineering consultant is working closely with Storm Water Services to develop and finalize the design and the construction plans.  Personnel from City of Charlotte, the engineering consultant, land surveyors, wetland specialists, and geotechnical engineers will be working in the area collecting information necessary to complete the design.
 
Permitting Phase (March 2012 - June 2012)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within CMU rights-of-way will be obtained during this phase. The permitting phase of a project may overlap other phases. 
 
Property Easement/Acquisition (Completed February 2012)
The City works with citizens and businesses to acquire Storm Drainage Easements (SDEs) and Temporary Construction Easements (TCEs). The City requests that SDEs and TCEs be donated to provide access to the affected properties to make the recommended improvements and provide future maintenance. The affected property owners provided the essential easements.
 
Bid Phase (June 2012 - December 2012)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process.  By state law, the lowest responsible bidder is awarded the construction contract.  The bid phase of a project typically lasts 5 to 6 months.
 
Construction Phase (March 2013 - October 2013)
Throughout construction, efforts will be made to minimize disruption to nearby property owners.  Construction of proposed improvements will be supervised by a City Inspector.  Notifications of key construction dates and will be mailed to residents prior to construction.  There are two noticeable phases on projects like this one: major construction and revegetation.  The major construction work will be completed in the first six to nine months, weather permitting.  Major construction involves earth work, concrete work, culvert installation, roadway repaving and other activities typically associated with a construction project.  After the major construction is complete, the revegetation phase will begin.  This phase takes a couple growing seasons and is susceptible to things like drought. 
 
Project Team
 
Chad Nussman
City Project Manager
704-336-5676

Amy Bice, E.I.
Watershed Area Manager
704-432-0965
 
Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183 
 
Newsletters