Home
Storm Water Projects
Drainage & Flooding
Pollution Prevention
Fees & Billing
Volunteer
Storm Water A-Z
Print this PageSite Feedback
Ashley Farm Pond

The Ashley Farm Pond Project will enhance water quality to downstream waters by replacing the existing concrete spillway, which has experienced cracking, spa​lling and seepage below the concrete slab and the failed low level pvc discharge conduit with a reinforced concrete riser structure and culvert. In addition, the dam will be rebuilt and stabilized. The pond is approximately 1-acre in size and is located in the Ashley Farm subdivision in south Charlotte. The Ashley Farm Pond project is currently in the Construction Preparation Phase.

Objectives:

- Provide water quality benefits by rehabilitating an existing, degraded pond.
- Repair the dam to a safe and functional state.

Cost: $1,130,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.

The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Ashley Farm Pond Project through the phases listed below. Specific work is conducted during each phase with an emphasis made on public involvement throughout the entire project.

Ashley Farm CIP area map 

Feasibility/Conceptual Design Phase (Started March 2012 - Completed September 2012)
During the feasibility/conceptual design phase of the Ashley Farm Pond Project, CMSWS evaluated the existing conditions of the pond and developed a conceptual design. This design was presented at a property owner meeting on July 26, 2012. The conceptual design will be used as the basis for design.

Property Easement Acquisition (Completed July 2013)
The City's real estate staff will work with citizens to acquire Storm Drainage Easements (SDEs). The City requests that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance.

In addition to SDEs, temporary construction easements (TCEs) are needed to access work areas during construction and future maintenance. Also, sanitary sewer easements (SSEs) will be acquired for sanitary sewer work necessitated by the proposed conceptual design.

The easement acquisition phase of a project typically lasts 8 to 12 months. However, the actual duration of the acquisition phase depends upon property owner coordination and cooperation.

Design Phase (Started November 2012 – Completed October 2013)
Detailed construction drawings and specifications will be prepared for the Ashley Farm Pond project. Numerous details will be finalized, including the outlet structure, dam stabilization, potential utility relocations, and potential landscape changes. Personnel from City of Charlotte, the engineering consultant, land surveyors, wetland specialists, and geotechnical engineers will be working in the area collecting information necessary to complete the design. The design phase of a pond project typically lasts 12 to24 months. However, the design is not considered complete until all permits are obtained as the regulatory agencies may provide input which can influence the final design.

Permitting Phase (Started February 2013 - Completed May 2013)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. The permitting phase of a project may overlap other phases.

Bid Phase (Started October 2013 - Completed April 2014)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 5 to 6 months.

Construction Phase (End by Summer 2015)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates will be mailed to residents prior to construction.  

Project Team 

Tom Purvis, P.E.
Project Manager
704-336-3660

Amy Bice, E.I.
Watershed Area Manager
704-432-0965

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183

Newsletters

June 2014​  
February 2014​ 
October 2013  
June 2013  
December 2012  
August 2012  
March 2012