Cost: $800,000
Please note that the project costs includes all costs associated with the project such as planning and design, utility relocation, construction, signalization, permits and landscaping.
The Engineering & Property Management (E&PM) project team will manage the Fifth Street Sidewalk Project through a four stage process.
Click here to learn how City projects are selected, designed and built.
Traffic Control:
Construction for 5th Street sidewalk and N. College Street storm drainage work will begin in early May. During this time, temporary traffic control will exist between 4th Street and 6th Street on North College Street and on 5th Street between Church Street and Brevard Street.
Project Contacts:
Len Chapman, PE, Project Manager, 704-336-6750
Ashton Watson, PE, CDOT Planning and Design, 704-432-4638