In addition to the CLT 2015 development program, there are other projects at various stages of implementation. When complete, CLT will look very different than it does today and use more modern and efficient technology to meet customers’ needs and expectations.
As these projects become active, they will be added to the
main construction page.
Business Valet Deck II
Airfield:
Terminal Ramp Expansion (West) I
Concourse Expansions:
Concourse A Annex
Concourse B
Concourse E
Business Valet Deck II | Status: |
Under Design |
| Description: |
Due to the popularity of CLT’s Business Valet services and forecasted passenger growth, a second Business Valet Parking Deck will be built. The deck will be located on the west side of the existing Business Valet Deck along Wilkinson Boulevard.
Land clearing began in summer 2012. Grading for the 3,200-space deck is complete and construction will commence in June. |
| Duration: |
12 months |
| Milestones: |
Bid Opening May 2013 Award Contract June 2013 Construction July 2013 – June 2014 Operational June 2014 |
| Cost: |
$50,000,000 |
| Funding Source: |
2013 GARBS |
Terminal Ramp Expansion (West) I | Status: |
Preliminary Engineering Underway |
| Description: |
This project will design and construct an additional aircraft ramp that will accommodate a future four-gate concourse (Concourse A North Expansion). The ramp expansion project responds to the demand for increased aviation activity and additional air service to the region over time. |
| Duration: |
14 months |
| Milestones: |
Design March – June 2013 Advertise for bids July 2013 Award contract August 2013 Construction August 2013 – October 2014 |
| Cost: |
$7,000,000 |
| Funding Source: |
2013 GARBS Federal AIP Grant |
Concourse A Annex | Status: |
Planned |
| Description: |
This project plans for the construction of four additional gates north of Concourse A and will accommodate expanding air service. |
| Duration: |
9 months |
| Milestones: |
Design April – October 2013 Advertise for bids November 2013 Award contract December 2013 Construction January – September 2014 |
| Cost: |
$18,000,000 |
| Funding Source: |
2013 GARBS |
Concourse B | Status: |
Planned |
| Description: |
This project will provide for design and construction of an additional 10 gates on Concourse B. |
| Duration: |
31 months |
| Milestones: |
Design April – October 2013 Advertise for bids November 2013 Award contract December 2013 Construction January 2014 – July 2016 |
| Cost: |
$70,000,000 |
| Funding Source: |
2013 GARBS |
Concourse E | Status: |
Planned |
| Description: |
This project will add up to six gates for a total of up to 42. The project will also add jet bridges to the remaining gates. |
| Duration: |
14 months |
| Milestones: |
Design April – September 2013 Advertise for bids October 2013 Award contract November 2013 Construction January 2014 – March 2015 |
| Cost: |
$34,112,500 |
| Funding Source: |
2013 GARBS |