Phase 1 (between Tyvola Road and Randolph Road) - under construction
Phase 2 (between Randolph Road and Country Club Drive) - to start construction Summer 2010.
Phase 3 (between Country Club Drive and Harris Boulevard)- To Be Determined.
Other Links:
Link to Storm Water Cherokee / Scotland project and Briar Creek Stream Restoration.
Construction Update: Colony Road Work Schedule Change
Due to recent inclimate weather, Charlotte-Mecklenburg Schools were closed Monday, Feb. 1. CMS students will make up this snow day Monday, Feb. 15, or Presidents' Day. Because of this, the contractor will not close and cross Colony Road that weekend, as previously scheduled. The Colony Road work has been rescheduled for the week of Spring Break, Friday, April 2 - Friday, April 9. Our goal is to close the road for only a portion of the week. More information will be sent once the work dates and the road closing are finalized.
Please keep in mind that crews are still working on other construction activities, including blasting, trenching and pipe installation on the Myers Park High School campus.
Charlotte-Mecklenburg Utilities will continue to update residents and school officials of any future schedule changes or delays.
Revised Schedule
Residents can expect the following schedule for construction work at the high school:
Now - end of March: blasting, trenching and pipe installation on the Myers Park High School campus
April 2 - 9: Colony Road work
Rest of April: complete section on Myers Park High School campus and on Myers Park Country Club side of Colony Road
Please note that construction schedules are dynamic and susceptible to change
See below files for updates.
Safety - Please remember that any area along the creek that has been cleared is part of the active construction site. For safety reasons, pedestrians are not allowed in these areas or anywhere on the construction site. Parents, please make sure that your children are aware of the hazards and know to stay clear of this area.
Newsletter (January 2010)
Newsletter(October 2008), Newsletter(June 2008)
Newsletter and Project Map(July 2007). Aerial view of project
Frequently Asked Questions about Blasting.pdf
Oscar Renda Contracting, Inc. and Rockdale Pipeline, Inc. were selected as contractors for construction of Phase 1.
Crews continue to work under Myers Park High School. Once pipe is completed in this section, sections of 80-year old sewer pipe will be abandoned. Residents throughout the project will once again see construction trucks and crews during this time.
Phases 2
Customers along Briar Creek between Randolph Road and Country Club Drive have attended a public meetings about the alignment. More public meetins will be held before construction begins. Construction will start around Summer 2010.
Phase 3 will be designed and installed afterwards. Check this web page for updates on maps, schedule and public meetings. You can also click on 'Notify Me' at the top right corner to receive an email when this page is updated.