Business eServices Government Visitors Departments
 

Stonebridge Pond Enhancement

The Stonebridge Pond Enhancement Project will enhance water quality to downstream waters by repairing and stabilizing the dam and embankment and dredging sediment that has accumulated in the pond.  The project is currently in the Design Phase.

Objectives:
- Provide water quality benefits by rehabilitating an existing, degraded pond.
- Provide an urban storm water BMP.

Cost:  $1,400,000
Please note that this figure includes all costs associated with the project such as planning and design, utility relocation, consultant fees, construction, permits and landscaping.

The Charlotte-Mecklenburg Storm Water Services (CMSWS) project team will manage the Stonebridge Pond Rehabilitation Project through the phases listed below.  Specific work is conducted during each phase while an emphasis is made on public involvement throughout the entire project.

Stonebridge Pond Enhancement


Planning Phase (Completed June 2008)

During the planning phase of the Andover Storm Drainage Project, questionnaires and public meetings were used to obtain input from property owners.  Several improvement alternatives were developed and evaluated to determine the best solution.  A recommended alternative was selected and used as a guide for the design. 

Design Phase (TBD)
Detailed construction drawings are prepared for the projects.  Numerous details will be finalized, including embankment repair and stabilization, disposal processes, outlet sizes, utility relocations, and landscape changes.

Permitting Phase (TBD)
During the permitting phase, the required water quality permits are obtained from Federal and State governments.  Other permits such as permission to work within CMU and rights-of-way and Floodplain encroachment areas will be obtained during this phase.  The permitting phase of a project may overlap other phases.

Property Easement/Acquisition (Completed January 2009)
The City's real estate staff worked with citizens to acquire Storm Drainage Easements (SDEs).  The City requested that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance. 
In addition to SDEs, temporary construction easements are needed to access work areas.  The easement acquisition phase of a project typically lasts 8 to 12 months.

Bid Phase (TBD)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process.  By state law, the lowest responsible bidder is awarded the construction contract.  The bid phase of a project typically lasts 4 to 5 months.

Construction Phase (TBD)
Throughout construction, efforts will be made to minimize disruption to nearby property owners.  Construction of proposed improvements will be supervised by City inspectors.  Notifications of key construction dates and will be mailed to residents prior to construction.  Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.

Project Team 

Kate Labadorf, P.E.
City Project Manager
704-336-3653

Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183