Planning Phase (TBD)
City Staff is working with W.K. Dickson to identify, evaluate, and recommend improvements to stabilize the creek throughout the City View neighborhood. Storm Water Services is negotiating the scope, fees and schedule with W.K. Dickson to finish the planning phase for this project.
Design Phase (Time frame TBD)
During the design phase, construction drawings for the alternative selected during the planning phase are developed. Many details must be addressed including the determination of specific pipe sizes and alignments, channel widths and lining types, inlet sizes and locations, utility relocations, and easement locations. The design phase of a project typically lasts 21 to 34 months.
Permitting Phase (Time frame TBD)
During the permitting phase, the required water quality permits are obtained from Federal and State governments. Other permits such as permission to work within railroad and NCDOT rights-of-way will be obtained during this phase. The permitting phase of a project typically lasts 3 to 9 months. The permitting phase of a project may overlap other phases.
Property Easement/Acquisition (Time frame TBD)
The City's real estate staff works with citizens and businesses to acquire Storm Drainage Easements (SDEs). The City requests that SDEs be donated to provide access to your property to make the recommended improvements and provide future maintenance. In addition to SDEs, temporary construction easements may be needed to access work areas. The bid phase will begin after all easements are acquired. The easement acquisition phase of a project typically lasts 8 to 12 months.
Bid Phase (Time frame TBD)
During the bid phase, the final plans will be circulated to qualified contractors for a competitive bidding process. By state law, the lowest responsible bidder is awarded the construction contract. The bid phase of a project typically lasts 4 to 5 months.
Construction Phase (Time frame TBD)
Throughout construction, efforts will be made to minimize disruption to nearby property owners. Construction of proposed improvements will be supervised by City inspectors. Notifications of key construction dates and will be mailed to residents prior to construction. Because projects vary in size, the typical construction phase of a project can last from 3 months to over 2 years.
Project Team
Chad Nussman
City Project Manager
704-336-5676
Amy Bice, E.I.
Watershed Area Manager
704-432-0965
Matthew Gustis, P.E.
City Engineering Team Program Manager
704-336-6183
Newsletters
June 2009
February 2009
October 2008
May 2008