Robert L. Smith District Park
|
1604 Little Rock Road
Northwest Park District
Get Directions
Park Master Plan
Phase I Site Plan
|
|
Scope:
- Phase I of design and construction will include: 3 soccer fields, 1 practice field, 1 playground and 1 restroom/picnic shelter building.
Status:
- Construction began April 10, 2006 and is projected to be completed within 275 calendar days.
- Sprigging and irrigation will take place between February 2007 and July 2007.
- Soccer Fields will potentially be ready for play in Fall 2007.
|
Timeline:
- 1999 General Obligation Bonds
- 1/19/1999: 1st Community Workshop to receive community input on the Master Plan.
- 2/16/1999: 2nd Community Workshop to present conceptual plan.
- Summer 2000: Master Plan approved by PRC and BOCC.
- 11/28/2000: Community Workshop to discuss Phase I of development.
- 7/2001: Notice to proceed with Design
- 1/2002: 50% Design Completed
- 9/2004: 75% Design Competed
- 7/2005: 100% Design Completed
- 9/2005: Pre-bid Meeting
- 9/2005: Bid Opening
- 10/2005: All bids rejected due to invalid bid bond.
- 1/2006: Bid Opening re-advertised.
- 1/31/2006: Pre-bid meeting.
- 2/21/2006: Bid Opening
- 3/21/2006: BOCC approval of Contract
- 4/5/2006: Pre-construction meeting.
|
Contacts:
- Joyce L. Figueroa, Parks Planner, Mecklenburg County Park and Recreation Department, 704-336-5485
- Laura Gallaguer, Project Manager, Mecklenburg County Real Estate Services, 704-336-4567
- Consultant, HadenStanziale
- General Contractor, T.K. Browne Construction Company, Inc.
|
|