| LOCATION/ADDRESS: |
8045 Harrisburg Road, Charlotte, NC |
| PARK DISTRICT: |
East |
| DESIGN CONSULTANT: |
In-house Park and Recreation Park Planning Staff |
| CONTRACTOR: |
|
| PROJECT HISTORY: |
Project funds were identified from the 2004 Park Bond Referendum and will help meet the demand for soccer fields in the eastern section of Mecklenburg County. Two synthetic turf soccer fields will greatly expand play opportunity in all seasons. |
| PROJECT SCOPE: |
2 synthetic turf soccer fields and parking |
| STATUS/TIMELINE: |
Construction is 95 % complete with an expected opening Spring, 2009 |
| PARK PLANNER: |
For issues regarding construction or design contact
David Nelson 704- 336-8455 David.Nelson@MecklenburgCountyNC.gov
For all other issues, please contact the facility manager
|
|
|