Optimist Park Sidewalk Project

A 2002 Area Plan Project

This project will provide pedestrian access along East 15th Street from Davidson Street to Myers Street and to the greenway.

The pedestrian improvements will include:

  • 2',6" curb and gutter and 6' sidewalk at back of curb from Davidson Street to Alexander Street
  • 2',6" curb and gutter, 6' sidewalk and an 8' planting strip from Alexander Street to Myers Street.

Interlocking modular block walls will be used to minimize property impacts at 1200 N. Davidson Street and 615 E. 15th Street.  There will also be some catch basin replacements and adjustments. 

 
 


Optimist Park Sidewalk
This project will provide pedestrian access along East 15th Street from Davidson Street to Myers Street and to the greenway.

What's happened? Construction is complete.

What's next? Landscaping will be installed in January/February 2009.

Who to contact:  Valerie Hanes, 704-336-3628

 
 

 


Project Background
An Area Plan for Optimist Park was adopted in 2002 in response to participants who supported the planning process.  Area residents indicated the need for sidewalks to link Optimist Park to surrounding communities near the Greenway.  The purpose of this plan is to address the livability and long term viability of Optimist Park by developing strategies to address the neighborhood's physical, social and economic conditions.  This neighborhood serves as a gateway to the Center City from north Charlotte.

Cost:  $275,000
Project costs typically include all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping. 

The Engineering & Property Management (E&PM) project team will manage the Optimist Park Sidewalk project through a four stage process.  Click here to learn more about how City projects are selected, designed and built.