Business eServices Government Visitors Departments
 
graphic banner
New Bern Sidewalk Project

A South Corridor Infrastructure Project (SCIP)

 

This project will improve pedestrian access to the New Bern Light Rail Transit Station.  Sidewalk with accessible sidewalk ramps will be constructed along Melbourne Court from Marsh Road to Marion, along Griffith Street from Tryon Street to New Bern Street, along New Bern Street from Griffith to the Light Rail Station, and along portions of Tryon Street from Clanton Road to Remount Road.  Intersection improvements for pedestrians will also be constructed at Tryon/Clanton, Tryon/Griffith, and Tryon/Remount. 
 

Objectives:

  • Construct sidewalk and accessible sidewalk ramps
  • Install improved pedestrian crossing signals
  • Install painted crosswalks at intersections listed above

Project Contacts:
Sharon Buchanan, Engineering Project Manager, 704-336-2044
Tom Sorrentino, PE, Transportation Project Manager, 704-336-3934
John Howard, Planning Commission, 704-336-0198

 
Cost:  $1,410,000
Please note that the project cost includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  
 
The Engineering & Property Management (E&PM) project team managed the New Bern Sidewalk Project through the stages listed below.  Specific work was conducted during each stage with an emphasis on public involvement during the planning and design phases. 
 
Planning & Design Phase (Complete) 
City staff worked with the Gannett Fleming Consultant Team to plan the improvements to New Bern Road.  The plans were based on safety, cost, benefits, traffic analysis and a public involvement process.  The public involvement process allowed citizens and nearby businesses to provide input at public meetings.  On November 30, 2004, a public meeting was held to present the design to area residents and businesses.
 
Real Estate Phase (Complete)
The City's Real Estate staff worked with citizens and businesses to acquire right of way and property easements needed for construction work.
 
Bid Phase (Complete)
During the bid phase, final specifications were prepared and quantities of material were determined.  The City of Charlotte followed the North Carolina state regulations and selected United Construction Inc., the lowest responsible bidder.
 
Construction Phase (Completed in May 2006)
E&PM staff worked closely with the contractor and property owners to ensure right of way agreements were followed.
color bar graphic
View Text-Only
Print This Page
Events Calendar
311 Web Requests
Maps/GIS Locator
Notify Me
Site Help
Feedback

logo
Official City of Charlotte & Mecklenburg County Government Web Site