Business eServices Government Visitors Departments
 

Fred D. Alexander Boulevard

Section B: Freedom Drive to Valleydale Road
Section C: Valleydale to Brookshire Boulevard (Highway 16)
Fred D. Alexander Boulevard extends from Freedom Drive to Valleydale Road (Section B), and from Valleydale Road to Brookshire Boulevard (Section C), a total distance of approximately two miles.  A four-lane, median divided, curb and gutter roadway will be constructed on new location.  Bicycle lanes and sidewalks along the project will accommodate cyclists and pedestrians. 
 
Section B1 (Currently under construction)
This section includes a bridge over Old Mt. Holly Road and and Mount Holly Road, and construction of a ramp to Old Mt. Holly Road. Construction should be complete by December 2010.
Section B2 (Currently in the bid phase)
Construction of this section will begin in November 2009 and be completed by December 2011.  This section extends from Freedom Drive to the ramp at Old Mt Holly Road.
Section C (Currently in the bid phase)
construction will begin in November 2009 and be completed by June 2011.  This section extends from Valleydale Road to Brookshire Boulevard.
 
 


Fred D. Alexander
This project will provide a new circumferential road in Northwest Charlotte.

What's happened?The first phase of Fred D. Alexander Boulevard Project is under construction. Two other sections are in the bid phase. Funding for construction was approved in the 2006 and 2008 transportation bonds.

What's next? Construction on two sections will start by November 2009.

Who to contact? Imad Fakhreddin, 704-336-7926

 
 

Objectives:

  • Construct another good circumferential road in the northwestern quadrant of the City (I-485 would be the other facility)
  • Provide community connectivity by providing sidewalks and bicycle facilities
  • Reduce congestion and improve safety
  • Provide a grade separated intersection at proposed Fred D. Alexander, Mount Holly Road, CSX Rail Road and Old Mount Holly Road 
  • Construct two bridges, one over the main Rail line to the CSX facility and one over a Rail road spur.
  • Close two at-grade Rail Road crossings.

Cost (for both sections):  $49,400,000
Please note that this figure includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fee, construction, and landscaping.  
 
The Engineering & Property Management (E&PM) project team will manage the Fred D. Alexander Boulevard Project (Sections B and C) through a four stage process.  Specific work is conducted during each stage with an emphasis on public involvement during the planning and design phases.  Click here to learn how City projects are selected, designed and built. 

Planning & Design Phase
City staff worked with STV/Ralph Whitehead Associates, Inc. (Section B) and HDR Engineering (Section C) to plan and design the improvements to both Fred D. Alexander Boulevard Projects.  These plans were based on safety, cost, benefits, traffic analysis and a public involvement process that allowed citizens and nearby businesses to provide input at public meetings. 
 
Funding for Real Estate Acquisition and Utility Relocation was approved in the November 2004 Bond Referendum (approximately $5.8 million).  Funding for the first phase of construction ($20 million - bridge over the CSX Railroad @ Mount Holly Road) was approved in the November 2006 Bond Referendum.  An additional $21.5 million was included in the 2008 Bond Referendum to complete the construction of Fred D. Alexander Boulevard between Freedom Drive and Brookshire Boulevard.

Click here to view the January 2007 postcard.
Click here to view the December 2008 postcard.
 
Real Estate
The City's Real Estate staff completed the acquisition of the right of way and property easements needed for construction work. 
 
Bid Phase (see schedule above for the two sections)
During the bid phase, final specifications and special provisions will be prepared and quantities of material will be determined.  The City of Charlotte follows the North Carolina state regulations and selects the lowest, responsible bidder. 
 
Construction Phase (see schedule above for the two sections)
E&PM staff will work closely with the contractors and property owners to ensure right of way agreements are followed.
Project Contacts:
Imad Fakhreddin, P.E., Engineering Project Manager, 704-336-7926
Veronica Wallace P.E., Transportation Project Manager, 704-336-7401