Business eServices Government Visitors Departments
 
Tyvola Road Intersection Project

A South Corridor Infrastructure Project (SCIP)

map of Tyvola Road project
 
   
 

This project will provide a better pedestrian and bicycle environment at and between three intersections: Tyvola Road and Old Pineville Road; Tyvola Road and South Boulevard; and South Boulevard and Grover Road.  Pedestrians will benefit from a planted median, landscaping, and new sidewalks with planting strips.  Additionally, bicycle lanes will be installed along Tyvola Road from South Boulevard to Old Pineville Road.

Objectives:

  • Improve pedestrian safety with pedestrian countdown signals, refuge islands and improved sidewalks/crosswalks
  • Provide a safe environment for bicycles
  • Beautify Tyvola Road 

Project Contacts:
Joe Frey, PE, Engineering Project Manager, 704-336-5276
Veronica Wallace, PE, Transportation Project Manager, 704-336-7401
Dan Thilo, Planning Commission, 704-336-8321

Cost:  $3,400,000
Please note that the project cost will include all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  
 
The Engineering & Property Management (E&PM) project team will manage the Tyvola Road Signature Intersection Project through the stages listed below.  Specific work is conducted during each stage with an emphasis on public involvement during the planning and design phases. 
 
Planning & Design Phase (Completed)
City staff worked with the Gannett Fleming consultant team to plan the improvements to Tyvola Road.  The plans were based on safety, cost, benefits, traffic analysis and a public involvement process.  The public involvement process allowed citizens and nearby businesses to provide input at two public meetings.  Click here to view the final concept plan for Tyvola Road.
 
Real Estate Phase (Completed)
The City's Real Estate staff worked with citizens and businesses to acquire right of way and property easements needed for construction work.
 
Bid Phase (Completed)
During the bid phase, final specifications were prepared and quantities of material were determined.  The City of Charlotte followed the North Carolina state regulations and selected Allied Resources, the lowest responsible bidder.
 
Construction Phase (Completed Fall 2006)
E&PM staff worked closely with the contractor and property owners to ensure right of way agreements were followed.
image of bike lane
Bike lanes (similar to the one below) will be installed along Tyvola Road.