Archdale Signature Project

A South Corridor Infrastructure Project

 
   
 

This project added bicycle lanes and sidewalk on both sides of Archdale Drive from Cherrycrest Lane to Montpelier Road.  Sidewalk was built on the north side of Archdale Drive between its two intersections with Cherrycrest Lane and on the east side of Ingleside Drive from Archdale Drive to Emerywood Drive.  Other project features included street and pedestrian lighting and landscaping.   

Objectives:

  • To improve bicycle and pedestrian access, safety and comfort levels within the Archdale Station Area
  • To promote transit-oriented development within the Archdale Station Area

Project Contacts:
Todd Thorne, Engineering Project Manager, 704-353-0993
Veronica Wallace, PE, Transportation Project Manager, 704-336-7401

Cost:  $5,580,000
Please note that the project cost included all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.  
 
The Engineering & Property Management (E&PM) project team managed the Archdale Signature Project through the stages listed below.  Specific work was conducted during each stage with an emphasis on public involvement during the planning and design phases. 
 
Planning & Design Phase (Fall 2003 - Summer 2005) 
City staff worked with the Gannett Fleming Consultant Team to plan the improvements to the Archdale Signature Intersection.  The plans were based on safety, cost, benefits, traffic analysis and a public involvement process.  The public involvement process allowed citizens and nearby businesses to provide input at 3 public meetings. 

Real Estate Phase (Spring 2005 - Fall 2005)
The City's Real Estate staff worked with citizens and businesses to acquire right of way and property easements needed for construction work.

Bid Phase (Winter 2005 - Spring 2006)
During the bid phase, final specifications were prepared and quantities of material were determined.  The City of Charlotte followed the North Carolina state regulations and selected the lowest, responsible bidder. 
 
Construction Phase (Spring 2006 - Spring 2007)
E&PM staff worked closely with the Contractor and property owners to ensure right of way agreements were followed.

Landscape Phase (December 2006 - Spring 2007)
E&PM's contractor installed trees, shrubs and groundcover throughout the project limits.