Central Avenue Streetscape @ Eastland Mall
|
Part of the City's Eastside Strategy Plan
This project is funded through the Charlotte Mecklenburg Planning Commission and will continue the improvements of past streetscape work on Central Avenue to the area of Eastland Mall (Sharon Amity Road to Reddman Road).
This streetscape project will narrow Central Avenue in the area of the mall to match the completed streetscape work in other sections of Central Avenue. The completed project will include landscaped medians which will allow pedestrians to safely cross the street. The work will also include bicycle lanes, widened sidewalks, planting strips, and landscaping.
Objectives:
- Increased opportunities for landscaping.
- Improvements to both street and sidewalks for increased pedestrian and traffic safety.
- Updated street and pedestrian lighting.
|
| |
| |
Central Avenue @ Eastland Mall This project will provide street and pedestrian improvements along Central Avenue between Sharon Amity Road and Albemarle Road.
What's happened? City staff worked with Kimley-Horn and Associations to design the streetscape imrovements. Planning and design is complete. Real estate acquisition is underway.
What's next? Construction will begin in 2008.
Who to contact? Keith Carpenter, 704-336-3650
|
|
|
| |
|
Cost: $4,000,000 Please note that this figure includes all costs associated with the project such as planning and design, acquiring the right of way, utility relocation, consultant fees, construction, signalization, permits and landscaping.
The Engineering & Property Management (E&PM) project team managed the Central Avenue Streetscape Project through a four stage process. Specific work is conducted during each stage with an emphasis on public involvement during the planning and design phases. Click here to learn how City projects are selected, designed and built.
|
|
|
|
|