Capital Improvement Projects and Investments
This map represents some of the water and sewer projects completed in past five years to serve the needs of our community.




‚Äč

Water and Sewer Improvements
Historically, CMUD has built projects to meet demands generated by high system growth. During the past few fiscal years, focus has shifted to maintenance as the economy has slowed. More than 85 percent of the system was constructed after 1980 and the older portions are in growing need of rehab or replacement.

Significant Projects 2012-2013 and Total Project Cost*
Completed New Franklin Water Treatment Plant Raw Water Reservoir........................... $30M
Ongoing Water Line Rehabilitation...................................................................................$9.5M
Completed Vest Water Treatment Plant & Patton Ave. Water Tank Rehab ..................... $2M
Designed Statesville Road Water Transmission Main....................................................... $7M
Designed Steele Creek Pump Station Replacement......................................................... $42M
Started Phase I Irwin Creek Wastewater Treatment Plant Upgrades..............................$40.5M
Ongoing Sewer Rehabilitation......................................................................................... $11M
Started Mallard Creek Wastewater Treatment Plant Clarifier.......................................... $6M
Designed Ramah Creek Trunk Sewer...............................................................................$6.5M

Rehabilitation
CMUD invests more than $20 million to restore and maintain aging water and sewer
lines each year.

Fire Protection
CMUD provides water for fire protection throughout Mecklenburg County and is responsible for repairing more than 16,000 hydrants and valves.